Practice questions covering critical path analysis from this specification. Attempt the questions below; real-paper references for this topic are being imported.
Questions to attempt
6 questions on Critical path analysis, each with its mark scheme and worked method. Reveal the answer when you have had a go.
D1-4.1 · Modelling of a project by an activity network, from a precedence table.
Q1
ORIGINAL
Year 1
Year 1: this is the AS subject content the exam board publishes, which is what most schools teach in Year 12.
1.
A project has the precedence table: A and B have no predecessors; C has immediate predecessor A; D has immediate predecessors A and B; E has immediate predecessor C; F has immediate predecessor C; G has immediate predecessors D and E; H has immediate predecessors F and G. Describe an activity network for this project, giving the event numbers of every arc.
(7)
(Total for Question 1 is 7 marks)
D1-4.2 · Completion of the precedence table for a given activity network.
Q2
ORIGINAL
Year 1
Year 1: this is the AS subject content the exam board publishes, which is what most schools teach in Year 12.
2.
An activity network on events 1 to 6 has: A from 1 to 2; B from 1 to 3; a dummy from 2 to 3; C from 2 to 4; D from 3 to 4; E from 3 to 5; F from 4 to 5; G from 5 to 6. Write down the complete precedence table.
(7)
(Total for Question 2 is 7 marks)
D1-4.3 · Algorithm for finding the critical path. Earliest and latest event times. Earliest and latest start and finish times for activities. Identification of critical activities and critical path(s).
Q3
ORIGINAL
Year 1
Year 1: this is the AS subject content the exam board publishes, which is what most schools teach in Year 12.
3.
A project has activities with durations A=5, B=4, C=6, D=3, E=7, F=2, G=4, H=5 and precedence A: none; B: none; C: A; D: A and B; E: C; F: C; G: D and E; H: F and G. Find the project duration and the critical path.
(7)
(Total for Question 3 is 7 marks)
D1-4.4 · Calculation of the total float of an activity. Construction of Gantt (cascade) charts.
Q4
ORIGINAL
Year 1
Year 1: this is the AS subject content the exam board publishes, which is what most schools teach in Year 12.
4.
For a project of duration 24 with activities A=5, B=7, C=4, D=6, E=3, F=8, G=2, H=5 and precedence A: none; B: none; C: A; D: A; E: B; F: C and D; G: D and E; H: F and G, calculate the total float of every activity.
(7)
(Total for Question 4 is 7 marks)
D1-4.5 · Construct resource histograms (including resource levelling) based on the number of workers required to complete each activity.
Q5
ORIGINAL
Year 2
Year 2: this is content the exam board adds beyond the AS subject content, for the full A-level.
5.
A project has activities A of duration 3 needing 2 workers, B of duration 4 needing 1 worker, C of duration 2 needing 3 workers, D of duration 5 needing 2 workers and E of duration 3 needing 1 worker, with precedence A: none; B: none; C: A; D: B; E: C and D. Find the project duration and the critical activities.
(5)
(Total for Question 5 is 5 marks)
D1-4.6 · Scheduling the activities using the least number of workers required to complete the project.
Q6
ORIGINAL
Year 2
Year 2: this is content the exam board adds beyond the AS subject content, for the full A-level.
6.
A project has durations A=5, B=4, C=6, D=3, E=7, F=2, G=4, H=5 with precedence A: none; B: none; C: A; D: A and B; E: C; F: C; G: D and E; H: F and G. The critical time is 27 and the critical path is A, C, E, G, H. Find a lower bound for the number of workers and construct a schedule attaining it.
(8)
(Total for Question 6 is 8 marks)
Progress is saved on this device for guests and accounts right now; cross-device account sync is not live yet.
Real-paper references for this module are being imported — the questions above are the site's own, exam-faithful, marked.
Reference rows contain series, paper, question number, marks and classification metadata only. Pearson's question papers open on Pearson's own website.