Edexcel A-level Further Maths · Topic D1-4

Critical path analysis questions

Practice questions covering critical path analysis from this specification. Attempt the questions below; real-paper references for this topic are being imported.

Questions to attempt

6 questions on Critical path analysis, each with its mark scheme and worked method. Reveal the answer when you have had a go.

  1. D1-4.1 · Modelling of a project by an activity network, from a precedence table.

    Q1
    ORIGINAL
    Year 1
    Year 1: this is the AS subject content the exam board publishes, which is what most schools teach in Year 12.

    1.

    A project has the precedence table: AA and BB have no predecessors; CC has immediate predecessor AA; DD has immediate predecessors AA and BB; EE has immediate predecessor CC; FF has immediate predecessor CC; GG has immediate predecessors DD and EE; HH has immediate predecessors FF and GG. Describe an activity network for this project, giving the event numbers of every arc.

    (7)

    (Total for Question 1 is 7 marks)

  2. D1-4.2 · Completion of the precedence table for a given activity network.

    Q2
    ORIGINAL
    Year 1
    Year 1: this is the AS subject content the exam board publishes, which is what most schools teach in Year 12.

    2.

    An activity network on events 11 to 66 has: AA from 11 to 22; BB from 11 to 33; a dummy from 22 to 33; CC from 22 to 44; DD from 33 to 44; EE from 33 to 55; FF from 44 to 55; GG from 55 to 66. Write down the complete precedence table.

    (7)

    (Total for Question 2 is 7 marks)

  3. D1-4.3 · Algorithm for finding the critical path. Earliest and latest event times. Earliest and latest start and finish times for activities. Identification of critical activities and critical path(s).

    Q3
    ORIGINAL
    Year 1
    Year 1: this is the AS subject content the exam board publishes, which is what most schools teach in Year 12.

    3.

    A project has activities with durations A=5A=5, B=4B=4, C=6C=6, D=3D=3, E=7E=7, F=2F=2, G=4G=4, H=5H=5 and precedence AA: none; BB: none; CC: AA; DD: AA and BB; EE: CC; FF: CC; GG: DD and EE; HH: FF and GG. Find the project duration and the critical path.

    (7)

    (Total for Question 3 is 7 marks)

  4. D1-4.4 · Calculation of the total float of an activity. Construction of Gantt (cascade) charts.

    Q4
    ORIGINAL
    Year 1
    Year 1: this is the AS subject content the exam board publishes, which is what most schools teach in Year 12.

    4.

    For a project of duration 2424 with activities A=5A=5, B=7B=7, C=4C=4, D=6D=6, E=3E=3, F=8F=8, G=2G=2, H=5H=5 and precedence AA: none; BB: none; CC: AA; DD: AA; EE: BB; FF: CC and DD; GG: DD and EE; HH: FF and GG, calculate the total float of every activity.

    (7)

    (Total for Question 4 is 7 marks)

  5. D1-4.5 · Construct resource histograms (including resource levelling) based on the number of workers required to complete each activity.

    Q5
    ORIGINAL
    Year 2
    Year 2: this is content the exam board adds beyond the AS subject content, for the full A-level.

    5.

    A project has activities AA of duration 33 needing 22 workers, BB of duration 44 needing 11 worker, CC of duration 22 needing 33 workers, DD of duration 55 needing 22 workers and EE of duration 33 needing 11 worker, with precedence AA: none; BB: none; CC: AA; DD: BB; EE: CC and DD. Find the project duration and the critical activities.

    (5)

    (Total for Question 5 is 5 marks)

  6. D1-4.6 · Scheduling the activities using the least number of workers required to complete the project.

    Q6
    ORIGINAL
    Year 2
    Year 2: this is content the exam board adds beyond the AS subject content, for the full A-level.

    6.

    A project has durations A=5A=5, B=4B=4, C=6C=6, D=3D=3, E=7E=7, F=2F=2, G=4G=4, H=5H=5 with precedence AA: none; BB: none; CC: AA; DD: AA and BB; EE: CC; FF: CC; GG: DD and EE; HH: FF and GG. The critical time is 2727 and the critical path is AA, CC, EE, GG, HH. Find a lower bound for the number of workers and construct a schedule attaining it.

    (8)

    (Total for Question 6 is 8 marks)

Progress is saved on this device for guests and accounts right now; cross-device account sync is not live yet.

Printable question pack — D1-4 Critical path analysisAll 60 questions across 6 specification points — 54 more than the 6 above — with the full mark scheme. Guest accessible · browser print.

D1-4 Critical path analysis revision notes

Real-paper references

Real-paper references for this module are being imported — the questions above are the site's own, exam-faithful, marked.

Reference rows contain series, paper, question number, marks and classification metadata only. Pearson's question papers open on Pearson's own website.