1.
(3)
(Total for Question 1 is 3 marks)
Notes and three levels of exam-style practice for each registered specification point in this section.
Checked against Edexcel 9FM0 section D1-4. Review basis: the qualification registry sourced from the Pearson Edexcel Level 3 Advanced GCE in Further Mathematics (9FM0) specification; registry verification recorded 17 July 2026.
In the exam: Formulae booklet provided · calculator allowed in every paper
Open the printable packA self-report of how sure you feel. It does not measure mastery. Evidence from your answers reaches secure after the latest Tier 2/3 attempt is correct, with three correct distinct drills across at least two dates and two practice sources.
Explanation
A project has activities and with no predecessors, with immediate predecessor , and with immediate predecessors and . Explain why a dummy is needed and describe the network.
Answer: One dummy is needed, from the end of to the start of , because depends on both and while depends on only.
Common mistakes
Exam tip
Work down the precedence table one activity at a time and ask which activities must be complete before it starts; a dummy is needed exactly when two activities have overlapping but unequal predecessor sets.
1.
(3)
(Total for Question 1 is 3 marks)
1.
(7)
(Total for Question 1 is 7 marks)
1.
(7)
(Total for Question 1 is 7 marks)
This section: Evidence from your answers: 0/6 secureYour confidence: 0 self-rated secureTracker status: 0/6 secure, 0 shaky, 6 unseen
Overall: Evidence from your answers: 0/116 secureYour confidence: 0 self-rated secureTracker status: 0/116 secure, 0 shaky, 116 unseen
Progress is saved on this device for guests and accounts right now; cross-device account sync is not live yet.
A self-report of how sure you feel. It does not measure mastery. Evidence from your answers reaches secure after the latest Tier 2/3 attempt is correct, with three correct distinct drills across at least two dates and two practice sources.
Explanation
In a network, runs from event to event , runs from event to event , a dummy runs from event to event , leaves event and leaves event . Write down the precedence table.
Answer: : none; : none; : ; : and .
Common mistakes
Exam tip
Take the activities in the order they appear on the network and write the event each one leaves beside it; the table then follows from a single scan of the arcs entering those events.
1.
(3)
(Total for Question 1 is 3 marks)
1.
(7)
(Total for Question 1 is 7 marks)
1.
(8)
(Total for Question 1 is 8 marks)
A self-report of how sure you feel. It does not measure mastery. Evidence from your answers reaches secure after the latest Tier 2/3 attempt is correct, with three correct distinct drills across at least two dates and two practice sources.
Explanation
A project has of duration with no predecessors, of duration with no predecessors, of duration after , and of duration after and . Find the project duration and the critical path.
Answer: The project takes and the critical path is , , .
Common mistakes
Exam tip
Do the whole forward pass before starting the backward pass, and check that the latest time at the start event comes out as ; if it does not, there is an arithmetic error.
1.
(4)
(Total for Question 1 is 4 marks)
1.
(7)
(Total for Question 1 is 7 marks)
1.
(9)
(Total for Question 1 is 9 marks)
A self-report of how sure you feel. It does not measure mastery. Evidence from your answers reaches secure after the latest Tier 2/3 attempt is correct, with three correct distinct drills across at least two dates and two practice sources.
Explanation
An activity of duration runs from event to event . The earliest time at event is and the latest time at event is . Find its total float and describe its bar on a Gantt chart.
Answer: The total float is , and the activity is drawn as a block from to with a float window extending to .
Common mistakes
Exam tip
Write at the top of your working and substitute the three numbers explicitly; nearly all float errors come from picking the wrong event time.
1.
(2)
(Total for Question 1 is 2 marks)
1.
(7)
(Total for Question 1 is 7 marks)
1.
(9)
(Total for Question 1 is 9 marks)
A self-report of how sure you feel. It does not measure mastery. Evidence from your answers reaches secure after the latest Tier 2/3 attempt is correct, with three correct distinct drills across at least two dates and two practice sources.
Explanation
In a project of duration , activity needs workers on days to and activity needs workers on days to . Find the histogram heights and the peak.
Answer: The heights are and the peak is workers, on days and .
Common mistakes
Exam tip
Tabulate the interval each activity occupies before drawing anything; the histogram is then a column-by-column addition and mistakes are easy to spot.
1.
(3)
(Total for Question 1 is 3 marks)
1.
(5)
(Total for Question 1 is 5 marks)
1.
(9)
(Total for Question 1 is 9 marks)
A self-report of how sure you feel. It does not measure mastery. Evidence from your answers reaches secure after the latest Tier 2/3 attempt is correct, with three correct distinct drills across at least two dates and two practice sources.
Explanation
A project of critical time has activities totalling days of work, with critical path from to and from to , and non-critical activities of duration with window to and of duration with window to . Find the least number of workers and give a schedule.
Answer: Two workers suffice, with worker on then and worker on then .
Common mistakes
Exam tip
Give the critical path to a single worker first; that worker is then fully occupied for the whole project and the remaining activities are much easier to place.
1.
(2)
(Total for Question 1 is 2 marks)
1.
(8)
(Total for Question 1 is 8 marks)
1.
(9)
(Total for Question 1 is 9 marks)
Bring a tricky specification point or a recent answer, and we can work through the method and exam wording together.