Critical path analysis
Forward pass takes the largest, backward pass takes the smallest — then float picks out the critical activities.
Question
Every step worked, with the reasoning.
- 1Earliest starts: , , , ,
Forward pass: an activity starts only when all of its predecessors have finished, so take the largest finish time.
- 2, ; minimum completion time days
Continue the forward pass to the end of the project.
- 3Latest finishes: , , ,
Backward pass: an activity must finish by the latest start of every successor, so take the smallest.
- 4, ,
has two successors, (latest start 3) and (latest start 4).
- 5Total float latest finish duration earliest start: , , ; , , , each have float .
Check the zero floats: , , , .
- 6Critical path: , of length days
The zero-float activities form an unbroken chain from start to finish whose length equals the completion time.
Answer: 13 days; critical path ; total floats , ,