1.
(2)
(Total for Question 1 is 2 marks)
2 specification points · notes, questions, answers and worked methods
Checked against Edexcel 9FM0 section FS1-4. Review basis: the qualification registry sourced from the Pearson Edexcel Level 3 Advanced GCE in Further Mathematics (9FM0) specification; registry verification recorded 17 July 2026.
Explanation
Worked example
A process has claimed mean faults per day. Over independent days, faults occur. At the level, test whether the daily mean has increased, given that and .
Answer: There is sufficient evidence at the level that the daily mean fault rate has increased.
Common mistakes
Exam tip
A full test conclusion must name the significance level, evidence and contextual parameter direction.
1.
(2)
(Total for Question 1 is 2 marks)
2.
(4)
(Total for Question 2 is 4 marks)
1.
(7)
(Total for Question 1 is 7 marks)
2.
(6)
(Total for Question 2 is 6 marks)
3.
(7)
(Total for Question 3 is 7 marks)
1.
(8)
(Total for Question 1 is 8 marks)
2.
(8)
(Total for Question 2 is 8 marks)
3.
(8)
(Total for Question 3 is 8 marks)
4.
(8)
(Total for Question 4 is 8 marks)
5.
(8)
(Total for Question 5 is 8 marks)
Explanation
Worked example
Four independent geometric waiting times have common parameter . Their sum is . Test against . Explain which tail is critical and interpret a result in that tail.
Answer: Use the upper tail; a critical result gives evidence that the success probability is below .
Common mistakes
Exam tip
Before calculating a critical value, write one sentence linking larger or smaller to waiting-time direction.
1.
(3)
(Total for Question 1 is 3 marks)
2.
(3)
(Total for Question 2 is 3 marks)
1.
(7)
(Total for Question 1 is 7 marks)
2.
(6)
(Total for Question 2 is 6 marks)
3.
(6)
(Total for Question 3 is 6 marks)
1.
(8)
(Total for Question 1 is 8 marks)
2.
(8)
(Total for Question 2 is 8 marks)
3.
(8)
(Total for Question 3 is 8 marks)
4.
(8)
(Total for Question 4 is 8 marks)
5.
(7)
(Total for Question 5 is 7 marks)
Answers begin on a new printed page so the question pack can be completed without the solutions alongside it.
| Question | Scheme | Marks |
|---|---|---|
| 1 |
| 2 |
| (2 marks) | 2 | |
| Notes | ||
| The claim supplies the null value. The word 'increased' makes the alternative upper-tailed, so use . | ||
| 2 |
| 4 |
| (4 marks) | 4 | |
| Notes | ||
| An increase gives against . Under , the supplied region has probability , which is the chance of rejecting a true null hypothesis. The observation is critical, so reject in favour of an increased mean. | ||
| Question | Scheme | Marks |
|---|---|---|
| 1 |
| 7 |
| (7 marks) | 7 | |
| Notes | ||
| Under , the eight-hour total . Calculator tails give , while . Thus the critical region is and its size is . Since is not in the critical region, do not reject . | ||
| 2 |
| 6 |
| (6 marks) | 6 | |
| Notes | ||
| The exposure is hours and the observed total is . Assuming independent counts and a common constant hourly mean allows the four periods to be pooled. Under , the total . The upper-tail probability is to decimal places. Since , reject ; there is evidence that the hourly mean exceeds . | ||
| 3 |
| 7 |
| (7 marks) | 7 | |
| Notes | ||
| The alternative is lower-tailed because a decrease is being tested. Under , add the six independent tile counts to get . The size of the supplied critical region is . The data give , which lies in the supplied critical region. Therefore reject ; there is evidence at the level that the mean blemish count per tile has decreased. | ||
| Question | Scheme | Marks |
|---|---|---|
| 1 |
| 8 |
| (8 marks) | 8 | |
| Notes | ||
| Under , the total . A decrease requires the lower tail. The adjacent probabilities are and , so the critical region is with size . The observed total is not critical, so do not reject ; there is insufficient evidence of a decrease. | ||
| 2 |
| 8 |
| (8 marks) | 8 | |
| Notes | ||
| The observation period is hours and the observed total is . Under , . In the lower tail, but . In the upper tail, but . Thus the critical region is or , and the size of the test is . Since is critical, reject . | ||
| 3 |
| 8 |
| (8 marks) | 8 | |
| Notes | ||
| The total exposure is metres and the observed total is . Under , independence and a common constant rate give . The two probabilities in the given region are and , so the size is . The observed total lies in the upper part of the critical region, so reject ; there is evidence that the mean pinhole rate differs from per metre. | ||
| 4 |
| 8 |
| (8 marks) | 8 | |
| Notes | ||
| The observed total is . Under , adding the two independent counts gives . The adjacent upper-tail probabilities are and . Therefore is the smallest critical boundary precisely when . If , then and the rejection probability is . Since the observed total is , it lies in the critical region; there is evidence that the population mean customer count exceeds per hour. | ||
| 5 |
| 8 |
| (8 marks) | 8 | |
| Notes | ||
| Under , the independent genuine-signal and false-alert counts over hours have parameters and . Their total is therefore . The upper-tail probabilities are and , so the largest rejection region with size at most is and its size is to significant figures. Since the observed total is , reject ; there is evidence that the population mean genuine-signal rate exceeds per hour. | ||
| Question | Scheme | Marks |
|---|---|---|
| 1 |
| 3 |
| (3 marks) | 3 | |
| Notes | ||
| A fall gives the lower-tailed parameter alternative . Smaller success probabilities make the first success take longer, so evidence lies in the upper tail of the geometric variable. | ||
| 2 |
| 3 |
| (3 marks) | 3 | |
| Notes | ||
| A larger success probability shortens the wait, so use the lower tail. Under , , whereas . Hence the exact critical region is and its size is . The observed value is critical, so reject in favour of . | ||
| Question | Scheme | Marks |
|---|---|---|
| 1 |
| 7 |
| (7 marks) | 7 | |
| Notes | ||
| Under , is negative binomial with and . Since larger gives smaller sums, use the lower tail. Calculator probabilities give and , so the critical region is with size . Since , reject . | ||
| 2 |
| 6 |
| (6 marks) | 6 | |
| Notes | ||
| A smaller success probability increases the waiting time, so use the upper tail. Under , . Since but , the least possible threshold is . Thus the critical region is and the exact size of the test is . The observation is critical, so reject in favour of . | ||
| 3 |
| 6 |
| (6 marks) | 6 | |
| Notes | ||
| A smaller produces longer waits, so the upper tail supports . Under , the sum of three independent geometric stopping times is negative binomial with and . Hence the size of the supplied region is . The observed sum is , which is critical. Therefore reject ; there is evidence at the level that the scanners' population success probability is below . | ||
| Question | Scheme | Marks |
|---|---|---|
| 1 |
| 8 |
| (8 marks) | 8 | |
| Notes | ||
| Under , is negative binomial with and . A smaller makes larger sums more likely, so use the upper tail. The adjacent probabilities are and , so the critical region is with size . Since the observed sum is not critical, do not reject ; there is insufficient evidence that . | ||
| 2 |
| 8 |
| (8 marks) | 8 | |
| Notes | ||
| The sum of eight independent geometric variables is negative binomial with . Under , , while . Also , while . Hence the two tails are and , and the combined size of the test is . The observed sum is , which is not in either critical tail, so do not reject ; there is insufficient evidence that the response probability differs from . | ||
| 3 |
| 8 |
| (8 marks) | 8 | |
| Notes | ||
| The sum is . Under , the sum of seven independent geometric stopping times is negative binomial with and . The verified tails have probabilities and , so the size is . Because is discrete, adding the next attainable value to either rejection tail would take that tail over its allocated , so an exact overall size of cannot be attained with these tails. The model assumes the seven stopping times are independent and that every trial has the same constant pass probability . Since , reject ; there is evidence that the population pass probability for the calibration checks differs from . | ||
| 4 |
| 8 |
| (8 marks) | 8 | |
| Notes | ||
| The event means that there are at most one failed attempt before the th success. Under , its probability is . This is at and at , so is least. At , the rejection probability is . For the critical region is , so the observed sum gives evidence that the population recognition probability exceeds . | ||
| 5 |
| 7 |
| (7 marks) | 7 | |
| Notes | ||
| For a geometric variable, . Under , the given size therefore gives , so and the valid solution is . Since lies in the rejection region, there is evidence that the population recognition probability exceeds . When , the rejection probability, and hence the power, is . The complementary Type II error probability is . | ||